Case study / General contractor

BIM coordination ownership for a 416-unit apartment development.

ModelMason managed the composite model, clash-detection process, weekly coordination meetings, and issue follow-through for a large multifamily project with two post-tensioned podium levels.

The engagement

One accountable process across structural and MEPFP models.

Mechanical, Electrical, Plumbing, and Fire Protection subcontractors each developed their own models. Those systems also had to be checked against the structural model and the constraints of post-tensioned podium construction before field installation.

Project scale416 apartments
Structural systemTwo post-tensioned podium levels
Coordination scopeStructural + MEPFP
SoftwareNavisworks, AutoCAD MEP, and Revit

The coordination challenge

Bring independently developed trade models into one visible, accountable process.

Without a single coordination owner, the general contractor would have needed to combine models, run tests, prepare reports, lead meetings, assign actions, and repeatedly verify subcontractor updates.

What ModelMason owned

  • Combined and maintained the composite coordination model
  • Ran clash detection across structural and MEPFP systems
  • Prepared clash reports and a weekly issue log
  • Led weekly BIM coordination meetings
  • Assigned action items to each responsible subcontractor
  • Tracked updated models and open issues through closure

The result

Substantially less day-to-day coordination oversight was required from the GC team.

The general contractor retained visibility into status and major decisions while ModelMason managed the composite model, meetings, reporting, assignments, and follow-through. Subcontractors received clear responsibility for required updates, and unresolved issues remained visible before installation.

See the working record

Review a representative weekly coordination report.

The sample shows how priority clashes, trade ownership, decisions, and due dates can be kept visible.

Open sample PDF
Preview of the representative BIM coordination report

Ready for more capacity?

Let's identify the work your team should not be carrying alone.

Tell us where work is backing up. We will recommend a practical starting scope for a dedicated team member.

Connect with us